Map of completion dates
1. FOURTH  QUARTER  2021.
1. Add a lane to eastbound exit from I-80 to I-580/U.S. 395 southbound.
3. SECOND  QUARTER  2022.
3. Restripe eastbound I-80 from Wells Ave. to southbound I-580.
5. NEIGHBORHOOD WALLS FIRST QUARTER 2021. NOISE & VISUAL WALLS THIRD QUARTER 2021.
5. Build noise, visual, and neighborhood walls.
2. FOURTH  QUARTER  2021.
2. Add lanes and shoulders on I-580 southbound from I-80 to Vassar Street.
4. THIRD  QUARTER  2021.
4. Separate ramps for access to and from I-580 at  2nd St./Glendale Ave. and Mill St..
6. DECEMBER  2020.
6. Repair pavement on I-580 northbound.

EXPECTED COMPLETION DATES

Hover over box to see completion dates for each project area.

SUBJECT TO CHANGE

NDOT logo.png

All information is preliminary and subject to change

No homes will be impacted during the construction of SBX.